Claremont on the Park - Development Timeline
2024 | June | ADC Property announced to deliver Claremont Medical on Lot 512 |
2023 | November | Lot 512 released for sale by Offers Invited |
2023 | February |
Construction of a play space in front of Lucent Claremont beings. The Goods Shed changes name to FORM Gallery & Cafe |
2021 | September | Claremont on the Park wins Urban Renewal category in 2021 UDIA Awards for Excellence. |
2021 | August | Claremont on the Park named State Development of the Year (WA) in the national 2021 Property Council of Australia / Rider Levett Bucknell Innovation & Excellence Awards. |
2021 | May | Multiplex achieves practical completion of Oryx Communities' multi-generational seniors' precinct, The Queenslea. |
2019 | August | Start of construction on Oryx Communities' aged-care facility at Lot 506. |
2018 | March | Oryx Communities announced to deliver residential aged care at Lot 506. |
2017 | November | Claremont on the Park wins PIA WA 2017 Award for Best Planning Ideas - Small Project. |
2017 | October | Lot 506 released for sale by Expression of Interest. |
2017 | June |
The Goods Shed received the Heritage Award at the WA Architecture Awards. New Transperth car park for Claremont train station patrons open in the basement of the new Claremont Football Club. Claremont Football Club new clubrooms officially open and Claremont Tigers return to play at Claremont Oval. |
2017 | March | TRG Properties selected to develop Lot 508. |
2016 | October | Lot 508 released for sale by Offers Invited. |
2016 | August | The Goods Shed opened. |
2016 | April |
The Pocket by Georgiou Living is completed and first residents move in (Lot 503). Blackburne selected to develop Lot 509. |
2016 | March | Refurbishment work commenced on the historical Goods Shed and Stage 3 works were completed. |
2015 | November | Georgiou Developments, Blackburne and St Ives Group shortlisted for the second stage of the selection process to purchase and develop Lot 509. |
2015 | September | Construction works commenced on the new Claremont Football Club building (Lot 601). |
2015 | August | Lot 509 released for sale via an Expression of Interest process. |
2015 | July | FORM announced as future tenant of the Goods Shed. |
2015 | June - August | Partial temporary closure of Shenton Road. |
2015 | April | Changes to the existing Claremont train station car park occurred and a new temporary car park opened. |
2015 | March |
Goods Shed short term tenancy opportunity Expression of Interest closed. Stage 3 works commenced, involving the realignment of Shenton Road, undergrounding of Western Power lines and landscaping (12 month program). |
2015 | February | Mirvac launch the start of sales for The Grandstand apartments (Lot 504). |
2014 | November | Revo Fitness announced they have secured a site on Davies Road for a new fitness centre. |
2014 | June |
Stage 2 construction works completed. Mirvac selected to develop Lots 504 and 505. |
2013 | December | Stage 2 site construction works commenced. |
2013 | July | Georgiou Living selected to develop Lot 503, which will be the first apartment complex. |
2012 | December | Modifications to the structure plan along with estate Design Guidelines approved by the Town of Claremont. |
2012 | November | Stage 1 site works completed. |
2012 | October | Community Open Day and Design Guidelines and Detailed Area Plans submitted to Town of Claremont for approval. |
2012 | August | Lot 503 (first apartment site) released for sale via an Expression of Interest process. |
2020 | June | WAPC endorsed the Structure Plan. |